There are two main types of asbestos survey: a management survey, which finds asbestos that could be disturbed in everyday use, and a refurbishment and demolition (R&D) survey, which finds everything in the areas where building work is planned. Surveys we arrange for London homes and flats start from £325 + VAT, depending on property size.

Key facts from our London job records

  • There are two main types: a management survey for normal occupation, and a refurbishment and demolition (R&D) survey before building work.
  • Surveys we arrange in London start from £325 + VAT, depending on property size.
  • An R&D survey is intrusive: the surveyor lifts floors, opens walls and ceilings where work is planned.
  • Shared hallways, stairs and risers in a London block need a management survey as part of the freeholder's duty to manage.

Source: our own completed London jobs. Prices shown + VAT.

Choosing the right one saves money and delays. The wrong survey can mean paying twice, or builders downing tools halfway through a job.

The management survey

A management survey is designed for buildings in normal use. Its purpose is to locate, as far as reasonably practicable, asbestos that could be damaged or disturbed during day-to-day occupation, maintenance and minor works.

What it involves:

  • a walk-through of all accessible areas
  • samples taken from suspect materials, sent to a lab
  • some minor intrusion, such as lifting loose ceiling tiles or opening service cupboards
  • a report with a register of materials, their condition and a risk rating

It's the usual choice for the shared hallways and stairs of a block of flats, for HMOs, and for landlords who want a record before letting. It doesn't look behind walls or under fixed floors.

The refurbishment and demolition survey

An R&D survey is needed before any refurbishment, fit-out or demolition work. It's fully intrusive in the area being worked on: the surveyor may lift floorboards, cut into partitions, open up boxing and look into ceiling voids. The aim is to find all asbestos that the work could disturb.

What it means in practice:

  • the area usually needs to be empty, because the survey can be destructive
  • it covers only the rooms or parts being worked on, so you can scope it to a single kitchen or a whole house
  • the report lists everything found, so it can be removed before builders start

In a London flat, an R&D survey is common before a new kitchen, a bathroom refit, knocking through a wall, or a loft conversion.

Which survey do I need?

Your situationSurvey type
Buying a flat or house to live in, no work plannedUsually none, or a management survey for peace of mind
Letting a flat or HMOManagement survey
Common parts of a block (freeholder or RMC)Management survey
New kitchen, bathroom or rewireR&D survey of the rooms affected
Loft conversion or extensionR&D survey of the loft and affected walls
Full refurbishment or strip-outR&D survey of the whole property
Demolishing a garage or outbuildingR&D survey, or a sample test if it's a simple structure

For a single suspect item, such as one ceiling or a garage roof, a sample test is usually enough and costs much less. See asbestos testing in London.

How surveys work in London blocks and conversions

Surveying a flat often means dealing with the building as well as the flat. The surveyor may need access to a shared loft, a meter cupboard or a riser to complete the survey properly. Let the managing agent know the date, and ask whether the building already has a management survey; it may answer some questions before the surveyor arrives.

Where a building has several flats being refurbished, a freeholder may commission one R&D survey for shared areas and leave each leaseholder to survey their own flat.

What's in the report

Both survey types produce a written report including:

  • the scope, and any areas that couldn't be accessed
  • a list of every material sampled, where it is, and the lab result
  • a condition and risk assessment for each asbestos item
  • plans or photos showing locations
  • recommendations: leave and manage, repair, or remove

Keep the report. Builders, buyers and managing agents will ask for it.

Getting ready for the surveyor

A little preparation makes the visit quicker and the report more useful:

  • clear access to the loft hatch, meter cupboards, under-stairs space and any outbuildings
  • for an R&D survey, empty the rooms being surveyed and warn other occupants about noise and dust
  • tell the surveyor exactly what work is planned, with drawings if you have them
  • arrange keys or access for any shared areas the managing agent controls
  • note any areas you know were refitted recently, and roughly when

Areas the surveyor can't reach are listed as "not accessed" in the report and treated as if they could contain asbestos, which can hold up the builders later.

What surveys cost

Surveys we arrange start from £325 + VAT, depending on property size. A studio flat management survey sits at the lower end; a large house R&D survey with many rooms and samples costs more. We give a fixed price once we know the property type, size and which rooms the work covers. Our survey cost guide has more detail.

Next steps: read do I need an asbestos survey? or see our asbestos surveys page.

Frequently asked questions

What is the difference between a management and an R&D asbestos survey?

A management survey finds asbestos that could be disturbed in everyday use. A refurbishment and demolition survey is intrusive and finds all asbestos in the areas where building work is planned.

Do I need an R&D survey for a new kitchen?

If the property was built or refitted before 2000, a refurbishment survey of the kitchen is the sensible step, because the work will disturb walls, floors and ceilings.

How much does an asbestos survey cost in London?

Surveys we arrange start from £325 + VAT, depending on property size and the type of survey.

Can I live in my flat during an R&D survey?

Usually you can live in the rest of the flat, but the rooms being surveyed should be empty because the survey may damage finishes.

Does the communal part of my block need a survey?

Yes. The person responsible for the common parts must manage asbestos there, which normally starts with a management survey.

Service page: Asbestos surveys in London

Prices: every London price table · Areas: all 32 boroughs

Need a survey arranged?

Tell us the property type and size, and what work you are planning. Prices from £325 + VAT depending on property size.

Get a free quote

Three quick questions. Send photos after and we can usually fix a price within the hour.

Text usCall 07367 196665
Text ussend photosQuote form3 questionsCall07367 196665