Asbestos air testing measures how many fibres are in the air, and after licensed removal work the area can only be handed back once it passes a four-stage clearance with a result below 0.01 fibres per millilitre. After lower-risk, non-licensed jobs, such as a ceiling in a flat, a reassurance air test is optional but gives tenants, neighbours and managing agents written proof the area is clean.

Key facts from our London job records

  • Air testing measures the concentration of fibres in the air. The UK clearance indicator is below 0.01 fibres per millilitre.
  • A four-stage clearance, with a certificate of reoccupation, is required after licensed asbestos work.
  • After non-licensed work, a reassurance air test is optional but useful in occupied flats and HMOs.
  • Air tests are carried out by an independent analyst, not by the removal contractor.

Source: our own completed London jobs. Prices shown + VAT.

This guide explains the different tests, what a clearance certificate shows, and when each makes sense in a London home.

The types of asbestos air test

Background test. Taken before work starts to record normal fibre levels. Useful in occupied blocks or where neighbours might later raise concerns.

Leak test. Taken outside an enclosure during licensed work to check fibres aren't escaping.

Personal monitoring. Samples taken from the worker's breathing zone, to check their protective equipment is suitable.

Reassurance test. Taken after non-licensed work, or in an area where asbestos might have been disturbed, to confirm the air is clean.

Four-stage clearance. The formal test after licensed work, leading to a certificate of reoccupation.

How the four-stage clearance works

  1. Preliminary check. The analyst checks the job is complete and the paperwork matches the work done.
  2. Visual inspection. A thorough check inside the enclosure for any remaining debris or dust.
  3. Air test. Air is drawn through filters while surfaces are disturbed, and the filters are analysed. The result must be below the clearance indicator of 0.01 fibres per millilitre.
  4. Final assessment. After the enclosure is removed, a last check of the area and the route used for waste.

Only when all four stages pass is the certificate of reoccupation issued. The analyst must be independent of the contractor doing the removal.

When do I need an air test?

SituationAir test
Licensed work, such as AIB or lagging removalFour-stage clearance, required
Non-licensed removal in an occupied flatReassurance test, recommended
Accidental damage to suspect materialReassurance test after clean-up
Communal area work in a blockOften requested by the managing agent
Garage or shed roof outdoorsNot usually needed

Outdoors, fibres disperse quickly and testing tells you little. Indoors, especially in a flat with neighbours on every side, a reassurance test is often worth having.

Air testing in London flats and HMOs

In a block, the managing agent or freeholder may ask for air testing as a condition of consent, particularly where work affects a shared ceiling void or a communal hallway. In HMOs, landlords sometimes test before tenants move back into a room.

Plan the timing. The analyst needs access to the flat, and the test usually takes a few hours including set-up. In buildings with controlled parking, let the analyst know about permits and loading in advance.

Reading the certificate or report

A reassurance or clearance report should show:

  • the address and the exact area tested
  • the date, the analyst's name and their organisation
  • the sample locations and the volume of air sampled
  • the results in fibres per millilitre
  • a clear pass or fail against the clearance indicator

Keep it with your property documents. Buyers' solicitors and managing agents may ask for it.

What air testing doesn't tell you

An air test shows the air was clean when sampled. It doesn't confirm whether a material contains asbestos (that needs a bulk sample tested at a lab) or whether all asbestos has been found (that needs a survey). See our guides to asbestos testing in London and types of asbestos survey.

Air testing and the waste paperwork

Air testing and waste paperwork answer two different questions, and you want both. The air test shows the room was left clean. The waste consignment note shows where the asbestos went: it records the type and amount of waste, the carrier and the licensed site that accepted it. Every removal job we do comes with a consignment note.

If you're selling a flat, or a managing agent has asked for evidence, keep both documents together. A reassurance certificate with no consignment note, or the other way round, often prompts more questions.

Costs and timing

Reassurance tests are priced per visit, depending on the number of samples and the size of the area. Four-stage clearances are built into the price of licensed work. In either case, plan for the analyst's visit at the end of the job so the area can be handed back the same day where possible.

Arranging an air test

We arrange reassurance air tests with independent analysts alongside our removal work, and for licensed jobs the four-stage clearance is part of the plan from the start. Tell us about your building, who needs to see the result and any access rules, and we'll give you a price. Read do I need an asbestos survey? and asbestos insulating board for related situations.

Frequently asked questions

What is a clearance certificate for asbestos?

A certificate of reoccupation is issued by an independent analyst after licensed asbestos work, once the area passes a four-stage clearance including an air test below 0.01 fibres per millilitre.

Do I need an air test after Artex removal?

It isn't legally required after non-licensed work, but a reassurance test is useful in occupied flats or where neighbours, tenants or a managing agent want written proof.

Who carries out asbestos air testing?

An independent analyst. For a four-stage clearance, the analyst must be independent of the removal contractor.

How long does an asbestos air test take?

Usually a few hours on site, including set-up and sampling. Results for reassurance tests are often available the same day.

Can an air test tell me if my ceiling contains asbestos?

No. An air test measures fibres in the air. To find out if a material contains asbestos, a sample of it needs to be tested at a lab.

Service page: Asbestos testing in London

Prices: every London price table · Areas: all 32 boroughs

Need a survey arranged?

Tell us the property type and size, and what work you are planning. Prices from £325 + VAT depending on property size.

Get a free quote

Three quick questions. Send photos after and we can usually fix a price within the hour.

Text usCall 07367 196665
Text ussend photosQuote form3 questionsCall07367 196665